NYAB Strengthens Its Position in Swedish Grid Expansion
NYAB announced that they have signed a cooperation agreement with Svenska kraftnät for the construction of a new 400 kV power line of approximately 100 kilometers between Letsi and Svartbyn in Norrbotten. The project will be carried out in two phases. The now signed agreement covers phase 1, which includes planning and design. Phase 2, the significantly larger construction and commissioning phase, is planned to commence during Q1 2026 and conclude during Q4 2028.