Fortum - Accelerator of the Clean Energy Transition

Fortum has projects rolling in. They’re laying the groundwork for future customers in Finland and Sweden. In Poland, too, district heating plants are being renewed.

14 Likes

Things are slowly starting to happen at the Lakari plot. The latest updates are as follows,

”The EIA examines two alternatives:

ALT1: up to 10 data center halls, IT capacity of about 900 MW, and power capacity of about 1,300 MW.

ALT2: up to 8 halls, IT capacity of about 660 MW, and power capacity of about 950 MW.

According to the EIA program, the data center would be connected to the main grid via two 400 kV power lines from Fingrid’s Rauma substation.

The planned route includes:

about 900 meters of underground cabling

about 1.2 kilometers of overhead lines

two 400 kV connections”

And quickly now, before the whining and crying about electricity sufficiency starts: on-site power generation is also planned.

”The EIA examines generators to be located alongside the data center, whose combined thermal input could be up to:

ALT1: 3,250 MW

ALT2: 2,500 MW

They could be used as backup power or alternatively also during normal operations to generate electricity for the data center or to the power grid. Note that these are thermal inputs, not the electrical output of the generators.

Looks good!

6 Likes

If a 1,300 MW center comes to Lakari in Rauma, it would be the largest single one in Finland. Sure, the 2,000 MW at Isokangas in Ii is bigger, but that’s a cluster of centers. It’ll be exciting to hear which company will become the operator of Lakari. Fortum isn’t paving the ground there just for fun.

Today, a major shake-up in F’s executive management was also announced. They’re about to shift into a higher growth gear soon:

”Fortum will provide more details on its strategic direction, growth targets, financial metrics, and segment reporting next February. Our financial position is strong, and we are ready for the next phase of growth, Rauramo emphasizes.”

6 Likes

Based on past history, I have to wonder – what kind of stupidity is it this time?

9 Likes

Regarding Lakari, it’s worth following the takeaways from this event.

Dec 2, 5:00 PM–7:00 PM: Fortum’s public event at Rauma Hall. Remote participation is also possible.

2 Likes

Here are Pauli’s comments on how Fortum is revamping its business structure and leadership team to accelerate its growth strategy. :slight_smile:

2 Likes

Little bits and pieces of information here and there.

Rauman Energia Investigates Utilizing Data Center Waste Heat in the District Heating Network

11/27/2026

Rauman Energia is involved in investigating the utilization of waste heat from the Rauma Lakari data center project, developed by Fortum, in the district heating network. The data center’s peak electrical power requirement would be up to 1,300 megawatts, and the waste heat it generates on an annual basis would be more than 30 times the heat demand of the city of Rauma. Last year, Rauman Energia sold approximately 0.26 TWh of district heating, and opportunities to utilize the waste heat are being explored, even though district heating demand is low in the summer.

2 Likes